Saturday, 18 July 2015

Framing Day 71 - Painting!!!

The painters have arrived! They've been busy!

Looking into the one of the front bedrooms.



I never realised that the front windows were so close to the floor!




The side bedroom, overlooking the neighbours, hence the glazing.







Leading out into the terrace.

More detailing done, in preparation for rendering.

The main living room.


The dwarf door under the stairwell.

Windows for the theatre room. We were forced to have them for energy rating reasons.

Where a large TV will eventually go.

The 920mm double doors do look big!

Decorative columns into the study.


Friday, 10 July 2015

Framing Day 66 - More Hebel and Plumbing Updates

In the two days since the previous post, the minions had been busy.

Not only had the Hebel been put on the garage, there had also been additional plumbing works for the hot water service performed.


Hot Water Service location. ORG is the original ground level.


The colours change dramatically with the available light.

Wednesday, 8 July 2015

Framing Day 64 - Plumbing Updates

I should probably stop calling these Framing Day XX, but... Meh. At least it shows some form of linear progression.

A few days later, the plumbers had returned to do some more plumbing work.

They managed to line up the down pipe and storm water pipes!


Gas, Hot and Cold Water along with Power points.

Where the gas line enters the house.

Saturday, 4 July 2015

Framing Day 61 - Stairs in, Cabinetry In, Doors on!

It did not take long for the stairs to be put into place! The cabinetry was also put in.

The only change we made post site start, was to have the laundry door hung the other way (a zero cost variation). Our Site Supervisor was ok with this. Needless to say, the door was hung the wrong way. The door frame is made in the factory (they do not do it on site), and despite the many assurances to the contrary, it was hung the wrong way. I informed David, and I got "Oh No! You're kidding me!" Nope.







The missing panel was damaged and PD picked it up, and ordered a new one.




Now that's a galley sink! The AFA-768!

Not quite like the world of style.

A view of the dwarf door under the stairwell.

The door was still hung the wrong way.

The lounge has been walled in to make a theatre room. We've made a feature of the plumbing stack.

We have front doors!

I love that stairwell!

And it's detail.

The view from the terrace.


Showing the three coats of render.

Why is this not finished flush, why around the corner?

Quality Control of the Slab's Concrete - The Report

After much requesting, the quality report of the slab's concrete (as detailed in this post - Quality Control of the Slab's Concrete) finally arrived!






My personal suspicions are that these reports are generated regularly within Boral, it was the fact that an end client was requesting a copy is what threw them.

I never got any sense that neither should i not be asking nor should I be receiving a copy, more of a how do we get that?