Today, the guys were continuing to prepare the slab.
I popped around twice through out the day to see their progress. In the morning, they were putting the wood boxing around where the edge of the slab would actually be.
 |
| All of the support bracing is yet to be put in place. |
 |
| Looking at the rear of the slab, it is very high off the ground. |
 |
| Some very heavy reo-rod and normal mesh. Apologies for my finger! |
 |
| All of the different types used. |
When I arrived in the afternoon, they had completed the boxing and were well into the laying of the moisture barrier (thick black plastic) used to protect the slab.
 |
| The bracing has been completed. You can see the height of the slab. |
 |
| Still lots more to do. |
The pour is due for Friday and there is still much to do.